Ayana Heights Construction Progress for April 2025
April 30, 2025
Building E: Piling completed 100%.
Building F: Piling completed 100%.
Building G: Piling completed 100%.
Building H: Piling completed 100%.
Buildings E, F, G, and H: Pile cutting work completed 5%.
Building C: Excavation completed 100%, preparing for piling.