AYANA Heights Phuket – March 2025 Construction Progress

April 21, 2025

In March, piling work at AYANA Heights advanced across Buildings E, F, G, and H—bringing the project another step closer to delivering elevated luxury living.

Construction at AYANA Heights continues with strong momentum in March, as piling work progresses steadily across all four residential buildings in the current development phase.

Building E:

Piling work has reached 80% completion, marking substantial progress toward structural foundations and vertical development.

Building F:

At Building F, piling work is 40% complete. Activities remain on schedule, laying the groundwork for the upcoming stages of construction.

Building G:

Piling has been fully completed at Building G, representing a key milestone that clears the way for structural work to commence.

Building H:

Piling work is also 100% complete at Building H, setting the stage for the next phase in development.

As each building at AYANA Heights moves forward, the project continues to reflect the signature blend of luxury, engineering precision, and serene hillside living that defines the AYANA brand.